20-Year CapEx, OpEx, Dual-Chiller Plant, Structural Height Savings & Net Lettable Space Evaluation
Standard commercial office floor plate operating 10 hrs/day (2,600 EFLH/yr). Compares VAV against Radiant Ceiling + DOAS.
24/7 hospitality operation (18,000 m² GFA, 4,500 EFLH/yr) with dedicated high-temp chiller plant and silent guestroom cooling.
New-build development capturing slab-to-slab height savings (300 mm/floor) and +1.8% additional Net Lettable Area from smaller shafts.
| HVAC & Building Subsystem | VAV ($/m²) | Radiant ($/m²) | VAV Total | Radiant Total |
|---|---|---|---|---|
| 1a. Low-Temp Chiller Plant (6°C CHWS) VAV: 100% capacity | Radiant: DOAS dehumidification chiller |
$68,000 | $32,000 | ||
| 1b. Dedicated High-Temp Chiller Plant (16°C CHWS) 2nd Chiller Setup dedicated to sensible radiant cooling |
$0 | $48,000 | ||
| 2a. Primary Low-Temp CHW Piping & Pumps Chilled water risers & distribution to AHU/DOAS coils |
$34,000 | $18,000 | ||
| 2b. Secondary High-Temp Radiant Piping, Pumps & Manifolds 2nd Piping Network + PEX loops & zone mixing manifolds |
$0 | $36,000 | ||
| 3. Air Handling Units (VAV AHUs vs Compact DOAS) DOAS air volume is 65–70% smaller than VAV |
$52,000 | $28,000 | ||
| 4. Sheet-Metal Ductwork, VAV Boxes & Diffusers Downsized ventilation ductwork vs full-sized VAV ducts |
$74,000 | $26,000 | ||
| 5. Radiant Ceiling Panels / Embedded Hydronic Slabs Sensible radiant terminal surfaces |
$0 | $72,000 | ||
| 6. BMS Controls, Dew-Point Sensors & Commissioning | $24,000 | $28,000 | ||
| Subtotal Mechanical HVAC CapEx | $252/m² | $288/m² | $252,000 | $288,000 |
| 7. New-Build Floor-to-Floor Height Saving Credit ~300 mm slab-to-slab reduction per floor (curtain wall & structure savings) |
$0/m² | -$22/m² | $0 | -$22,000 |
| Net Construction CapEx (After Structural Height Credit) | $252/m² | $266/m² | $252,000 | $266,000 |